Reading: Multiple Choice, Single Answer · Question 972

Bottleneck and the limits

PTE · Reading · medium

Read the text and answer the multiple-choice question by selecting the correct response. Only one response is correct.

In a simplified production line, preparation can supply twenty components per hour, assembly can handle twelve, and inspection can clear eighteen. Every completed component must pass through all three stages. Assuming steady operation, sufficient material, and no other constraints, assembly limits the line's sustained output. Improving preparation alone can enlarge the queue before assembly without raising completed output. The relevant distinction is between making one operation faster and changing the active constraint on the whole process; an improvement at a constrained stage may also move the bottleneck rather than remove every limit.

If assembly capacity rises to twenty-four components per hour while the other capacities stay fixed, which statement follows under the assumptions?

  • Completed output stays at twelve per hour because changing one stage cannot affect a whole production line.
  • Completed output can reach twenty-four per hour because the original bottleneck has been improved to that capacity.
  • Preparation becomes the bottleneck at twenty per hour because it is now slower than assembly.
  • Inspection becomes the bottleneck at eighteen per hour, limiting sustained completed output despite the assembly improvement.