Two exhibition rooms require carpentry followed by painting. A planner schedules all carpentry in both rooms before any painting begins, explaining that painting must follow carpentry. The contractors agree with that requirement within each room, but point out that the rooms can be worked on independently by separate teams. Once carpentry finishes in the first room, its painters need not wait for the second. The proposed timetable turns a local dependency into a requirement for the whole project, adding a delay that the stated technical order does not itself demand.
What assumption makes the proposed timetable more restrictive than necessary?
- Painting each room requires its own carpentry to be complete first.
- Separate teams can carry out different kinds of work in different rooms.
- The two rooms may require different amounts of time for the same kind of work.
- A stage must be completed throughout the project before the next stage can begin anywhere.