Schedule with room for recovery

PTE · Reading · medium

Read the text and answer the question by selecting all the correct responses. More than one response is correct.

A project schedule that allocates every available hour to planned tasks may appear efficient, but it leaves little room to respond when an activity takes longer than expected. Some delays can be absorbed by moving independent work forward. Others affect a sequence of dependent tasks, so a small interruption can postpone several later stages. Consider a publication project in which layout depends on receiving final illustrations. Editing an unrelated section may continue while an illustration is delayed, but the affected pages cannot be completed in the same way. The schedule therefore needs to distinguish tasks that can overlap from tasks that require a specific predecessor to finish. Simply adding up estimated working hours does not describe all of these relationships. A recovery allowance can provide room for checking, corrections, or delays without immediately moving the final date. Such an allowance is not proof that the team expects to work slowly. It recognizes uncertainty and makes the intended margin visible. Its size should reflect the nature of the work rather than an arbitrary assumption that every task carries equal risk. A useful schedule consequently represents both effort and dependency. It helps the team identify which interruption matters most and where a change can be accommodated, instead of treating a fully occupied calendar as sufficient evidence of a robust plan.

Which statements about project scheduling are supported?

  • Including spare capacity proves that the team intends to work slowly.
  • Adding estimated hours alone captures every dependency between tasks.
  • Every delay necessarily stops all other work in the project.
  • Independent tasks may continue while a dependent sequence is interrupted.
  • A recovery allowance can accommodate uncertainty without immediately shifting the final date.
  • The consequences of a delay depend partly on how tasks are connected.