Reading: Multiple Choice, Multiple Answers · Question 474

Choosing whether to continue a project

PTE · Reading · hard

Read the text and answer the question by selecting all the correct responses. More than one response is correct.

A team deciding whether to continue a project may feel that stopping would waste the resources already spent. That concern is understandable, but past expenditure and future consequences answer different questions. Money that cannot be recovered by either continuing or stopping is a sunk cost. Its existence does not by itself show which available choice will produce the better result from now onward. Suppose a prototype has required considerable development but still faces an expensive technical obstacle. Continuing may be justified if the expected future benefits outweigh the additional resources and alternatives involved. It is not justified merely because the earlier investment was large. Equally, the sunk-cost principle does not imply that every difficult project should be abandoned. The work already completed may have created useful capabilities that change the prospects of future success. A careful decision therefore separates the irrecoverable expenditure from information about the project's present condition. Lessons learned, equipment acquired, and remaining opportunities can be relevant because they affect what happens next. They should not be confused with an emotional obligation to vindicate past spending. The question is whether continuation is the best current use of resources, not whether it can make the historical cost disappear. Recognizing this distinction allows a team to learn from its investment without treating the investment itself as a command to continue.

Which inferences follow from the author's argument?

  • Ignoring sunk costs requires ignoring all information gained during the project.
  • The principle necessarily favours abandonment whenever a technical obstacle appears.
  • A large irrecoverable investment is sufficient reason to continue a project.
  • Capabilities created by earlier work can still matter to a forward-looking decision.
  • Continuation should be assessed against future benefits, additional resources, and alternatives.
  • Learning from past work is compatible with refusing to let past expenditure dictate the decision.